No. 87-1097.United States Court of Appeals, Federal Circuit.
September 11, 1987.
Page 27
John Lukjanowicz, Oles, Morrison, Rinker, Stanislaw Ashbaugh, Seattle, Wash., argued for appellant. With him on the brief was Sam E. Baker, Jr.
Frank B. Flink, Jr., Commercial Litigation Branch, Dept. of Justice, Washington, D.C., argued for appellee. With him on the brief were Richard K. Willard, Asst. Atty. Gen., David M. Cohen, Director and M. Susan Burnett, Asst. Director. Also on the brief was Sabrina Simon, U.S. Army Corps of Engineers, Washington, D.C., of counsel.
Appeal from the Corps of Engineers Board of Contract Appeals.
Before MARKEY, Chief Judge, RICH and DAVIS, Circuit Judges.
DAVIS, Circuit Judge.
[1] The problem before us is whether the appellant-contractor, J-I-J Construction Company, Inc. (J-I-J or the contractor), has timely filed its appeal to this court from the decision of the Corps of Engineers Board of Contract Appeals (EngBCA or Board) dismissing as untimely J-I-J’s claim to that tribunal for attorney fees and expenses under the Equal Access to Justice Act (EAJA). We hold that the appeal to the court must be dismissed, due to late filing, as beyond our jurisdiction. I.
[2] The circumstances of J-I-J’s contract dispute with the Government are now important only for their relevance to the timeliness of the current appeal. On September 13, 1984, the EngBCA held under the Contract Disputes Act that the contractor was entitled to an equitable adjustment pursuant to the “Changes” clause of the contract because of defective specifications related to the use of a quarry designated by the Government. The amount of that adjustment was to be negotiated by the parties; if they could not agree, the Board would decide the amount. 84-3 BCA ¶ 17,619. The parties could not agree, and a new EngBCA hearing was begun on that subject, but before it concluded the parties stipulated the amount. The Board sustained the second (quantum) appeal “on stipulation” in the amount of $7,400,000, together with interest of $4,650,000 from April 12, 1985 to payment.
Page 28
only 30 days to file a fee application. The later controversy over the $75,000 deduction was held not to toll the finality of the earlier final decision. Because the fee application did not come until October 1985, it was held untimely. 86-3 BCA ¶ 19,126 (July 7, 1986). On November 6, 1986 J-I-J filed here its petition for review of the Board’s fee ruling.
II.
[5] The first and dispositive question is whether J-I-J’s appeal to this court was timely. 5 U.S.C. § 504(c)(2) provides that
[6] As pointed out in Part I, supra, the Board’s final decision denying fees (because of untimeliness) was issued on July 7, 1986; the contractor’s appeal to this court came on November 6, 1986 — some 122 days later, considerably beyond the allowable 30 days.[2] [7] In response, J-I-J asserts that the 30-day appeal provision of 5 U.S.C. § 504(c)(2), supra, applies only where the agency board has decided the merits of the fee application, not when the board has simply dismissed that application as untimely (without determining its merits). Emphasis is put on the words (in § 504(c)(2)) “determination of fees and other expenses” which are said to cover only an award (or denial of an award) on the merits. By a strained reading, the legislative history of the amended section is also said to show that Congress was then concerned solely with fee determinations on the merits.[3][i]f a party other than the United States is dissatisfied with a determination of fees and other expenses made under subsection (a) [which includes administrative agencies conducting “an adversary adjudication”[1] ] that party may, within 30 days after the determination is made, appeal the determination to the court of the United States having jurisdiction to review the merits of the underlying decision of the agency adversary adjudication.
Page 29
too late. And it would be most curious for Congress to leave that one circumstance without any appeal limit at all. In a word, the appeal period in 5 U.S.C. § 504(c)(2) applies to all fee rulings by contract appeals boards.
[9] It follows that the appeal in this case was filed much too late, this court therefore has no jurisdiction of the appeal, and the appeal must be dismissed.[4] [10] DISMISSED.Page 1075
NOTE: This disposition is nonprecedential. United States Court of Appeals for the Federal Circuit ______________________…
NOTE: This disposition is nonprecedential. United States Court of Appeals for the Federal Circuit ______________________…
United States Court of Appeals for the Federal Circuit ______________________ CORE WIRELESS LICENSING S.A.R.L., Plaintiff-Appellee…
?United States Court of Appeals for the Federal Circuit ______________________ MAXLINEAR, INC., Appellant v. CF…
?United States Court of Appeals for the Federal Circuit ______________________ JASON CARL KENNEDY, Plaintiff-Appellant v.…
In re GPAC INC. No. 93-1216.United States Court of Appeals, Federal Circuit. Decided June 20,…